Browse Projects

Shoreline - Seawall Projects (6 Found)
Spencer Smith Park

Completion Date: 1994, Location: Spencer Smith Park Burlington, Ontario, Canada

Shoreline Repairs & Improvements Improvements through demolition, New Steel Sheet Piling, Tie Backs Tremie Concrete Seals, Clear Stone Backfill,...

Bowmanville Fish Shoal

Completion Date: June 2000, Location: Blue Circle Cement Plant Bowmanville, Ontario, Canada

Construction of a underwater fish shoal using approx. 1400 t of armour stone

Burloak Shoreline Remediation Project

Completion Date: March 2003, Location: Burloak and Lakeshore, Burlington, Ontario, Canada

Construction of armour stone islands, 160m of an armour stone pier with concrete deck on support piles & 90m of an armour stone breakwater. Total...

Niagara Tunnel Facility Project

Completion Date: Fall 2007, Location: Niagara Falls, Ontario, Canada

Sub-contract to Dufferin Construction Company. Work includes construction of 1000 m of new precast concrete acceleration & shore approach walls, d...

Tate & Lyle North American Redpath Sugars

Completion Date: Spring 2005, Location: Toronto, Ontario, Canada

This project consists of repairing the South Wharf wall, including demolition, SSP Piles consisting of a double row of piles 50’ deep x 80&rsquo...

Burlington Channel Scour Protection

Completion Date: March 2007, Location: Burlington, Ontario, Canada

Placement of 23,400m² of Geotextile and 32,000 tons of stone.

Featured Projects

16th Avenue Phase 2 Trunk Sewer

Completion Date: October 2007, Location: Markham, Ontario, Canada

Regional Municipality of YorkDesign-Build Trunk Sanitary Sewer

Sheppard Subway Twin Tunnels

Completion Date: 2000, Location: Toronto, Ontario, Canada

Sheppard Subway Twin TunnelsContract SH-OO-C1Yonge Street to Don Mills Rd.

CP Rail Britt Wharf

Completion Date: September 2004, Location: Britt, Ontario, Canada

New Fuel Wharf, with concrete deck and steel pipe pile support.Completed in 60 days

Enwave Cooling Water Intake Pipe

Completion Date: September 2003, Location: Toronto Island, Ontario, Canada

Installation of 3 - 1600mm diameter HDPE Pipe x 5500m and associated on shore civil works

Raglan Mine-Deception Bay Wharf Rehabilitation

Completion Date: Fall 2007, Location: Deception Bay, Quebec, Canada

Rehabilitation of an existing wharf including dredging of clean and contaminated sediments, placing of mattress material, unloading, storing and monit...

Niagara Tunnel Facility Project

Completion Date: Fall 2007, Location: Niagara Falls, Ontario, Canada

Sub-contract to Dufferin Construction Company. Work includes construction of 1000 m of new precast concrete acceleration & shore approach walls, d...

Bathurst Collector and Langstaff Trunk Sewer Project

Completion Date: November 2008, Location: Vaughan, Ontario, Canada

A design build project being completed by McNally / Aecon Joint Venture and MacViro Consultants Inc. The project includes 8625 m 2.74 m inner diamete...