Completion Date: October 2004, Location: Point Tupper, NS, Canada
Construction of a wharf for Coal Handling. Consisting 5 concrete cribs, 2 bridge spans and 11 pile support piers
CP Rail Britt WharfCompletion Date: September 2004, Location: Britt, Ontario, Canada
New Fuel Wharf, with concrete deck and steel pipe pile support. Completed in 60 days
Bear Head LNG TerminalCompletion Date: Spring 2007, Location: Point Tupper, Nova Scotia, Canada
The marine terminal, a Design/Build project, will receive ships containing liquefied natural gas delivered from overseas. The jetty terminal shall be ...
Raglan Mine-Deception Bay Wharf RehabilitationCompletion Date: Fall 2007, Location: Deception Bay, Quebec, Canada
Rehabilitation of an existing wharf including dredging of clean and contaminated sediments, placing of mattress material, unloading, storing and monit...
Fundy Gypsum HansportCompletion Date: July 2003, Location: Hantsport, NS, Canada
Demolition of existing wharf structure and construction of a new wharf consisting of 10 pile supported dolphins.
Martin Marietta Wharf FacilityCompletion Date: December 2005, Location: Aulds Cove, NS, Canada
Steel Sheet Pile Bulkhead and Loadout Support Structure Construction of 650 foot SSP marginal wharf and new ship loader foundation.
Wallace Cove Wharf FacilityCompletion Date: September 2006, Location: Wallace Cove, NS, Canada
New Ferry Terminal consisting of a pipe pile supported wharf and lift bridge ramp. This structure is the mainland terminal for the Grand Manan Ferry.
Shell Canada LimitedCompletion Date: April 2007, Location: Corunna, Ontario, Canada
Repair Shell Canada Refinery North Dock. This project consisted of demolition of the damaged areas and total dock reconstruction including 50 No.&ndas...