CP Rail Britt Wharf

CP Rail Britt Wharf

Description

New Fuel Wharf, with concrete deck and steel pipe pile support.
Completed in 60 days

Equipment

McNo 102 Sectional Barge
American 9260 100 Ton Crane
Northwest 70D 80 Ton Crane
Northwest 50D 50 Ton Crane
Cat 325 Excavator
Cat IT28G Rubber Tire Loader

Method

Drilled 37 steel pipe piles, 800mm into rock with H-15 rotary head & fixed leads. Drilled 37 holes 5m into rock for 35mm tension bars and grouted. Fabricated temporary shoring for work off piles to form deck structure. Formed and poured 240m3 concrete deck structure. Completed 150m of shoreline protection and walkways, plus all mechanical piping to facilitate unloading of fuel.

Location

Britt, Ontario, Canada

Owner

CP Rail

Consultant

Hatch Mott MacDonald

Completion Date

September 2004

Contract Value

$2,000,000.00

Featured Projects

16th Avenue Phase 2 Trunk Sewer

Completion Date: October 2007, Location: Markham, Ontario, Canada

Regional Municipality of YorkDesign-Build Trunk Sanitary Sewer

Sheppard Subway Twin Tunnels

Completion Date: 2000, Location: Toronto, Ontario, Canada

Sheppard Subway Twin TunnelsContract SH-OO-C1Yonge Street to Don Mills Rd.

CP Rail Britt Wharf

Completion Date: September 2004, Location: Britt, Ontario, Canada

New Fuel Wharf, with concrete deck and steel pipe pile support.Completed in 60 days

Enwave Cooling Water Intake Pipe

Completion Date: September 2003, Location: Toronto Island, Ontario, Canada

Installation of 3 - 1600mm diameter HDPE Pipe x 5500m and associated on shore civil works

Raglan Mine-Deception Bay Wharf Rehabilitation

Completion Date: Fall 2007, Location: Deception Bay, Quebec, Canada

Rehabilitation of an existing wharf including dredging of clean and contaminated sediments, placing of mattress material, unloading, storing and monit...

Niagara Tunnel Facility Project

Completion Date: Fall 2007, Location: Niagara Falls, Ontario, Canada

Sub-contract to Dufferin Construction Company. Work includes construction of 1000 m of new precast concrete acceleration & shore approach walls, d...

Bathurst Collector and Langstaff Trunk Sewer Project

Completion Date: November 2008, Location: Vaughan, Ontario, Canada

A design build project being completed by McNally / Aecon Joint Venture and MacViro Consultants Inc. The project includes 8625 m 2.74 m inner diamete...