Enwave Cooling Water Intake Pipe

Enwave Cooling Water Intake Pipe

Description

Installation of 3 - 1600mm diameter HDPE Pipe x 5500m and associated on shore civil works

Equipment

Canadian Argosy Dredge w/ 2400 Lima Crane
McNally Olympic Barge w/ Manitowoc Crane
John Holden Hydraulic Dredge
Derrick #1 Barge w/ NW 190 Crane
800 cy Dump Scow
Sandra Mary Tug - 1300HP
Mr. Joe Tug - 1100HP
Bagotville Tug - 865 HP
R.C.L. 11 Tug - 600HP

Method

Fuse and test approx. 18,000m of pipeline in Belleville Yard. Tow lines in individual lengths of approx. 1,600m to the site just off Toronto Island.
Dredged trench to approx. 700m off the shore, and installed near shore pipeline.
Floated each 5,000m deep lake line to alignment. Anchored and sank pipe into place using a controlled method. Connected both pipes together.
Constructed valve chambers & pipeline connections to existing pumping station by open cut methods.

Location

Toronto Island, Ontario, Canada

Owner

Enwave District Energy

Consultant

Necso Canada Inc

Completion Date

September 2003

Contract Value

$30,000,000.00

Featured Projects

16th Avenue Phase 2 Trunk Sewer

Completion Date: October 2007, Location: Markham, Ontario, Canada

Regional Municipality of YorkDesign-Build Trunk Sanitary Sewer

Sheppard Subway Twin Tunnels

Completion Date: 2000, Location: Toronto, Ontario, Canada

Sheppard Subway Twin TunnelsContract SH-OO-C1Yonge Street to Don Mills Rd.

CP Rail Britt Wharf

Completion Date: September 2004, Location: Britt, Ontario, Canada

New Fuel Wharf, with concrete deck and steel pipe pile support.Completed in 60 days

Enwave Cooling Water Intake Pipe

Completion Date: September 2003, Location: Toronto Island, Ontario, Canada

Installation of 3 - 1600mm diameter HDPE Pipe x 5500m and associated on shore civil works

Raglan Mine-Deception Bay Wharf Rehabilitation

Completion Date: Fall 2007, Location: Deception Bay, Quebec, Canada

Rehabilitation of an existing wharf including dredging of clean and contaminated sediments, placing of mattress material, unloading, storing and monit...

Niagara Tunnel Facility Project

Completion Date: Fall 2007, Location: Niagara Falls, Ontario, Canada

Sub-contract to Dufferin Construction Company. Work includes construction of 1000 m of new precast concrete acceleration & shore approach walls, d...

Bathurst Collector and Langstaff Trunk Sewer Project

Completion Date: November 2008, Location: Vaughan, Ontario, Canada

A design build project being completed by McNally / Aecon Joint Venture and MacViro Consultants Inc. The project includes 8625 m 2.74 m inner diamete...