Bathurst Collector and Langstaff Trunk Sewer Project

Bathurst Collector and Langstaff Trunk Sewer Project

Description

A design build project being completed by McNally / Aecon Joint Venture and MacViro Consultants Inc. The project includes 8625 m 2.74 m inner diameter tunnel and 6 access shafts.

Three tunnel drives are being completed on the project, two for the Bathurst Sewer and one for the Langstaff Sewer. A main mining shaft is located at the mid-point of the Bathurst Sewer, from which the first of three TBMs was launched south for a 2550 m drive in January 2007. The TBM will be removed at the south limit and launched north from the main shaft for the remaining 2550 m. For the Langstaff tunnel, the TBM will be launched from the western limit for a 3525 m drive east to intersect the Bathurst tunnel.

Equipment

Two 3.25 m diameter Lovat EPB TBMs

Tunnel Dimensions

2.74 m finished tunnel

Geology

The tunnels range from 9 m to 30 m in depth, and will be constructed through till, sand and silty clay deposits with water heads up to 1.5 bar

Final Support

Precast concrete segments are being used as the final tunnel liner. The segments are manufactured in Ottawa by Boucher Precast and the Joint Venture Team

Location

Vaughan, Ontario, Canada

Owner

York Region

Completion Date

November 2008

Contract Value

$78,000,000.00

Featured Projects

16th Avenue Phase 2 Trunk Sewer

Completion Date: October 2007, Location: Markham, Ontario, Canada

Regional Municipality of YorkDesign-Build Trunk Sanitary Sewer

Sheppard Subway Twin Tunnels

Completion Date: 2000, Location: Toronto, Ontario, Canada

Sheppard Subway Twin TunnelsContract SH-OO-C1Yonge Street to Don Mills Rd.

CP Rail Britt Wharf

Completion Date: September 2004, Location: Britt, Ontario, Canada

New Fuel Wharf, with concrete deck and steel pipe pile support.Completed in 60 days

Enwave Cooling Water Intake Pipe

Completion Date: September 2003, Location: Toronto Island, Ontario, Canada

Installation of 3 - 1600mm diameter HDPE Pipe x 5500m and associated on shore civil works

Raglan Mine-Deception Bay Wharf Rehabilitation

Completion Date: Fall 2007, Location: Deception Bay, Quebec, Canada

Rehabilitation of an existing wharf including dredging of clean and contaminated sediments, placing of mattress material, unloading, storing and monit...

Niagara Tunnel Facility Project

Completion Date: Fall 2007, Location: Niagara Falls, Ontario, Canada

Sub-contract to Dufferin Construction Company. Work includes construction of 1000 m of new precast concrete acceleration & shore approach walls, d...

Bathurst Collector and Langstaff Trunk Sewer Project

Completion Date: November 2008, Location: Vaughan, Ontario, Canada

A design build project being completed by McNally / Aecon Joint Venture and MacViro Consultants Inc. The project includes 8625 m 2.74 m inner diamete...