Project Search

Fill out the name or description of the project you're looking for and click search.

Project Categories

Featured Projects

16th Avenue Phase 2 Trunk Sewer

Completion Date: October 2007, Location: Markham, Ontario, Canada

Regional Municipality of YorkDesign-Build Trunk Sanitary Sewer

Sheppard Subway Twin Tunnels

Completion Date: 2000, Location: Toronto, Ontario, Canada

Sheppard Subway Twin TunnelsContract SH-OO-C1Yonge Street to Don Mills Rd.

CP Rail Britt Wharf

Completion Date: September 2004, Location: Britt, Ontario, Canada

New Fuel Wharf, with concrete deck and steel pipe pile support.Completed in 60 days

Enwave Cooling Water Intake Pipe

Completion Date: September 2003, Location: Toronto Island, Ontario, Canada

Installation of 3 - 1600mm diameter HDPE Pipe x 5500m and associated on shore civil works

Raglan Mine-Deception Bay Wharf Rehabilitation

Completion Date: Fall 2007, Location: Deception Bay, Quebec, Canada

Rehabilitation of an existing wharf including dredging of clean and contaminated sediments, placing of mattress material, unloading, storing and monit...

Niagara Tunnel Facility Project

Completion Date: Fall 2007, Location: Niagara Falls, Ontario, Canada

Sub-contract to Dufferin Construction Company. Work includes construction of 1000 m of new precast concrete acceleration & shore approach walls, d...

Bathurst Collector and Langstaff Trunk Sewer Project

Completion Date: November 2008, Location: Vaughan, Ontario, Canada

A design build project being completed by McNally / Aecon Joint Venture and MacViro Consultants Inc. The project includes 8625 m 2.74 m inner diamete...